71 Freeway widening

Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

Rail bridge on segment 2 of Metro/Caltrans SR-71 widening project. Photo by Joe Linton/Streetsblog L.A.

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $61 million shortfall on a $40 million project.

Skywalkermeme

Stay in touch

Sign up for our free newsletter

More from Streetsblog Los Angeles

Kevin de León’s Cynical CD14 Debate Performance Shows How Little He’s Grown

De León repeatedly accused Jurado of being a liar who lacked substantive accomplishments while taking credit for a number of projects initiated prior to his tenure.

October 16, 2024

SGV Connect 129: Looking at Measures A and G

Both ballot measures need a simple majority to pass. SGV Connect will be back after the election to review what voters decided locally, regionally and across the state.

October 16, 2024

Metro Weekday Ridership Surpasses One Million

Metro ridership is at 86 percent of pre-pandemic levels, well ahead of the nationwide average of 76 percent

October 16, 2024

This Week In Livable Streets

Metro 405 Freeway widening meeting, weekend Metro A Line closures (Duarte to Azusa), Metro Rail to Rail path construction, and more

October 15, 2024
See all posts