Metro Approval Sets Stage for Construction of NoHo-Pasadena Bus Rapid Transit Line

$135M approved today will take the NoHo-Pasadena BRT project through the next two years. If this preconstruction phase goes as planned, the project will ramp up to full construction by 2027.

Rendering of NoHo-Pasadena center-running bus lanes design for Colorado Boulevard at Eagle Rock Blvd

LongBeachize_Ad_Concepts
This article supported by Los Angeles Bicycle Attorney as part of a general sponsorship package. All opinions in the article are that of the author, and do not necessarily reflect those of LABA. Click on the ad for more information.

This morning, the Metro Board of Directors approved moving into the construction phase of its overdue North Hollywood to Pasadena Bus Rapid Transit (BRT) project. The approval [staff report] was not for the full ~$320+million build-out, but for an initial $135 million "preconstruction" phase which finalizes the design and engineering, and starts $44.5 million worth of early construction activity.

Map of Metro North Hollywood to Pasadena Bus Rapid Transit project

The 19-mile, 22-station BRT project will connect the Metro A Line Memorial Park Station (in Pasadena) to the Metro B and G Line North Hollywood Station. The line will serve the cities of Burbank, Glendale, Pasadena, and the L.A. City neighborhoods of Eagle Rock and North Hollywood.

The project was funded in 2016 via Metro's Measure M sales tax, which programmed $266 million toward an anticipated 2020-23 groundbreaking and a 2022-25 opening. In 2018, the project received an additional $50 million in state transit capital grant funds.

The planning process was contentious, with some Eagle Rock residents fighting (including filing a lawsuit) against proposed Colorado Boulevard bus lanes. In 2022, Metro approved a fairly ambitious design, largely based on a context-sensitive pro-transit community design.

Some Burbank residents also later protested against bus lanes there.

NoHo-Pasadena BRT project status as of July 2024 - via Metro presentation

Since 2022, Metro has awarded two smaller contracts for NoHo-Pasadena BRT project management and architecture/engineering.

Meanwhile Metro construction costs crept upwards faster than sales tax revenue. Delays don't just mean local bus riders are missing out; if Metro doesn't get construction underway fairly soon, the project might not open until after the 2028 Olympic and Paralympic Games.

The approval of $135M today will take the project through the next two years. It brings onboard the BRT project Construction Manager/General Contractor (CM/GC) to get early work underway, mainly utility investigation and relocation. If this preconstruction (and final design) phase goes as planned, the project will ramp up into full construction by 2027.

Stay in touch

Sign up for our free newsletter

More from Streetsblog Los Angeles

Metro/Caltrans L.A. County Freeway Widening Accounted for Over 96 Percent of Recent Home Demolitions Statewide

Southern California has borne the brunt of harmful freeway widening, with L.A. County projects - where Caltrans partnered with Metro - resulting in mass demolition of homes and businesses

March 7, 2025

New Report Quantifies Five Years of Caltrans Freeway Expansion, including Demolitions

Over the past five year period, Caltrans tore down 623 homes and businesses, to make way for 553 new miles of highway lanes

March 5, 2025

Open Streets Return to El Monte this November

The route from North to South paints a picture of the town’s cultural fabric

March 5, 2025
See all posts